08/28/2019
|
Notice of Completion of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
08/28/2019
|
Notice of Completion of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
11/13/2017
|
Second correction to Notification to the start of construction electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
11/09/2017
|
Notification electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
02/09/2017
|
Notification of Start of Construction for the Delano-Scioto Trail 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
08/31/2016
|
Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
08/18/2016
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB |
08/02/2016
|
Correspondence - Officials Notification Compliance Filing (Tuscany) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
08/02/2016
|
Correspondence -Public Notification Compliance Filing (Tuscany) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
07/27/2016
|
Letter of Notification for the Delano-Scioto Trail 138k V Transmission Line Relocation Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
07/11/2016
|
In the matter of the -Pre-Application Notification Letter electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |