08/28/2019
|
Notice of Completion of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
05/07/2019
|
Notice of Adjustment for Good Hope-Harrison 138 kV Transmission Line Rebuild Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company, Inc. |
11/13/2017
|
Notification to inform that project commenced on October 1, 2016 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
10/28/2016
|
Staff Report of Investigation Supplement electronically filed by Mr. Matt Butler on behalf of Staff of OPSB |
10/21/2016
|
Letter of Notification - Supplemental LON electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/29/2016
|
Correspondence - Acceptance of All Staff Conditions electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/23/2016
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
09/22/2016
|
Proof of Pub - Good Hope-Harrison electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/07/2016
|
Notification - Public Notification Compliance Filing (GH-Harrison 1) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/07/2016
|
Notification - Officials Notification Compliance Filing (GH-Harrison 1) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/01/2016
|
Letter of Notification - part 10 of 10 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
09/01/2016
|
Letter of Notification - part 9 of 10 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
09/01/2016
|
Letter of Notification - part 8 of 10 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
09/01/2016
|
Letter of Notification - part 7 of 10 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
09/01/2016
|
Letter of Notification - part 6 of 10 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
09/01/2016
|
Letter of Notification - part 5 of 10 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company |
09/01/2016
|
Letter of Notification - part 4 of 10 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
09/01/2016
|
Letter of Notification - part 3 of 10 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company |
09/01/2016
|
Letter of Notification - part 2 of 2 electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
09/01/2016
|
In the matter of the Letter of Notification - part 1 of 10, Request for Expedited Treatment:
In the Matter of the Letter of Notification for the
Good Hope-Harrison #1 (Structure 206-Harrison) 138 kV Transmission Line Rebuild Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company |
08/18/2016
|
In the matter of the Pre-Application Notification Letter (Good Hope-Harrison) electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |