03/11/2019
|
Case Action Form closing case, In the Matter of Authorization for the Chicago Ft. Wayne and Eastern Railroad Corridor Project in Van Wert, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division |
03/11/2019
|
Memo Closing Case In the Matter of Authorization for the Chicago Ft. Wayne and Eastern Railroad Corridor Project in Van Wert, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. |
07/12/2017
|
Service Notice |
07/12/2017
|
Entry ordering that CFE's request for a six-month extension of the project
deadline be granted and the completion deadline for the CFE Corridor Project be extended to December 15,2017. |
06/27/2017
|
Service Notice |
06/27/2017
|
Attorney Examiner Entry granting CFE a 30-day extension of time to finish the project in accordance with Paragraph 9. - electronically filed by Sandra Coffey on behalf of James Lynn, Attorney Examiner, Public Utilities Commission of Ohio. |
06/20/2017
|
Memorandum of an Extension Request for the Chicago Ft. Wayne and Eastern Railroad Corridor Project in Van Wert, Ohio. electronically filed by Mrs. Jill A. Henry on behalf of PUCO/Rail Division. |
06/15/2017
|
Request for extension filed by Joseph Bolzenius on behalf of Patrick Engineering, Inc. for Chicago Ft. Wayne & Eastern Railroad. |
06/15/2016
|
Service Notice |
06/15/2016
|
Finding and Ordered, that the agreement be adopted and approved; that by September 15, 2016, CFE submit to the Commission's Railroad Division site plans and cost estimates for the project, and by September 22, 2016, file a letter in this docket advising that site plans and cost estimates have been submitted to the Commission. |
06/01/2016
|
In the matter of the application - Case entry for Chicago Ft. Wayne & Eastern Van Wert Corridor Project electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. |