12/02/2019
|
Case Action Form Closing Cases with an effective date of 12/2/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. |
08/28/2019
|
Notice of Completion of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
02/09/2017
|
Notification of Start of Construction for the Beatty Road Station Drainage Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
10/24/2016
|
Correspondence Letter Accepting Conditions in Staff Report electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
10/17/2016
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
10/12/2016
|
Notification - Public Notification Compliance Filing (Beatty Road Station) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
10/12/2016
|
Notification - Official Notification Compliance Filing (Beatty Road Station) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/30/2016
|
Construction Notice for the Beatty Road Station Drainage Improvements electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. (Part 2) |
09/30/2016
|
Request for expedited treatment and construction notice for the Beatty Road Station Drainage Improvements electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
03/11/2016
|
In the matter of the Notification of Pre-Application Notification Letter electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |