CASE NUMBER: 15-1713-EL-BNR
CASE DESCRIPTION: Chrysler-Dowling 138 kV Transmission Line Relocation for Roachton Road Roundabout
DOCUMENT SIGNED ON: 6/4/2024
DATE OF SERVICE: ________________________________________
04/01/2016 Letter of Notification that construction on this project started on January 4, 2016 and was completed on approximately March 18, 2016 filed by D.W.Parks, EngineerIV on behalf of FirstEnergy Service Company.
11/24/2015 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
10/19/2015 In the matter of the notification of ATSI for the Construction Notice of Chrysler-Dowling 138 kV Transmission Line Relocation For Roachton Road Roundabout.