DIS - Case Record for 14-1244-EL-BLN Skip to main content
      
      
CASE NUMBER: 14-1244-EL-BLN
CASE DESCRIPTION: Allen Junction – East Fayette 138 kV Transmission Rebuild Project
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
02/16/2017 Letter of Notification that the Lyons-East Fayette portion of this project was completed on February 13, 2017.
08/11/2016 Correspondence serving as notice from American Transmission Systems, Incorporated ("ATSI") of Supplemental Information of the continuation of construction for the Lyons to East Fayette portion of the above referenced Project filed by N. Bryksenkova, Engineer on behalf of FirstEnergy Service Company.
07/13/2015 Letter of notification that the Allen Junction-East Fayette was completed on December 30, 2014 filed by J. Thacker.
11/24/2014 Correspondence Supplemental Information Letter electronically filed by Ms. Jessica L Thacker on behalf of FirstEnergy Service Company
10/09/2014 Supplemental information to the Board concerning the construction of the Allen Junction-East Fayette Transmission Line Project filed by J. Thacker, on behalf of FirstEnergy Service Company.
09/11/2014 Letter of notification stating that the Allen Junction-East Fayette 138 kV Transmission Line Rebuild Project will begin on September 12, 2014 filed by J. Thacker on behalf of FirstEnergy Service Company.
08/11/2014 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
08/01/2014 Proof of Publication filed (Lucas & Fulton Counties)
07/18/2014 In the matter of the Letter of Notification of Allen Junction-East Fayette 138 kV Transmission Line Rebuild Project.