DIS - Case Record for 14-1107-EL-BLN Skip to main content
      
      
CASE NUMBER: 14-1107-EL-BLN
CASE DESCRIPTION: Harding-Perry 345 kV Transmission Line Loop to, and Expansion of, the Leroy Center Substation Project
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
12/23/2016 Notice stating that the project for the Harding-Perry 345kV Transmission Line Structure Loop to and Expansion of the Leroy Center Substation was completed on approximately December 6, 2016 filed by T. Turner on behalf of FirstEnergy Service Company.
12/01/2015 Site findings report filed by Travis Turner on behalf of FirstEnergy Service Company.
03/12/2015 Correspondence regarding start date of approximately March 16, 2015 for construction on this project filed by T. Turner on behalf of FirstEnergy.
02/23/2015 Notice of Acceptance of Proposed Staff Conditions electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
02/20/2015 Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB.
01/15/2015 Proof of publication filed. (Lake County)
12/01/2014 Amended Letter of Notification for Harding - Perry 345kV Transmission Line Loop to, and expansion of, Leroy Center Substation Project (Corrected Filing) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
12/01/2014 In the matter of the Letter of Notification for the Harding - Perry 345kV Transmission Line Loop to, and the expansion of, the Leroy Center Substation Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.