Date Filed | Summary | Pages |
02/22/2018 | Certificate 18-HYD-KY-GATS-0115 issued. | 3 |
02/21/2018 | Service Notice | 2 |
02/21/2018 | Finding & Order approving application and a certificate be issued.by the Commission's Docketing Division. | 6 |
02/26/2016 | Staff Review and Recommendation electronically filed by Mr. Stuart M Siegfried on behalf of PUCO Staff. | 4 |
05/06/2014 | Response to PUC Staff 2nd data request electronically filed by Mr. David H. Brown Kinloch on behalf of Lock 7 Hydro Partners, LLC. | 10 |
04/01/2014 | Response to Staff Initial Data Request electronically filed by Mr. David H Brown Kinloch on behalf of Lock 7 Hydro Partners, LLC | 13 |
03/28/2014 | Service Notice | 1 |
03/25/2014 | Attorney Examiner Entry suspending the automatic approval process for this application for certification as an eligible Ohio renewable energy resource generating facility; electronically filed by Vesta R. Miller on behalf of Richard M. Bulgrin, Attorney Examiner, Public Utilities Commission of Ohio. | 3 |
03/19/2014 | In the matter of the application for certification as an Ohio renewable energy resource generating facility for the Mother Ann Lee Hydroelectric Station electronically filed by Mr. David H. Brown Kinloch on behalf of Lock 7 Hydro Partners, LLC. | 15 |