04/13/2015
|
Case action form closing case with an effective date of 4/13/15. |
04/13/2015
|
Memo informing the Commission that Staff and Ann Arbor Railroad entered into an agreement
whereby new LED lights would be installed at 5 crossings in Toledo, Ohio and that the project requiring
that construction be completed by March 26, 2015 filed by Staff. |
03/28/2014
|
Service Notice |
03/26/2014
|
Finding and order stating that the Stipulation be adopted and approved and that the railroad proceed with and complete the project on or before March 26, 2015. |
02/27/2014
|
In the matter of a request for the Installation of New LED Lights at Five Ann Arbor Railroad crossings in Toledo, Ohio. |
|