DIS - Case Record for 14-0195-EL-BLN Skip to main content
      
      
CASE NUMBER: 14-0195-EL-BLN
CASE DESCRIPTION: OHIO POWER COMPANY / Azalea 138kV Transmission Line
DOCUMENT SIGNED ON: 4/25/2024
DATE OF SERVICE: ________________________________________
08/09/2019 Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.
08/09/2019 Case Action Form Close Case as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.
02/21/2017 Notification of Start of Construction and In-Service Date for the Azalea 138 kV Transmission Line Extension East Project electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company.
03/07/2014 Correspondence -Acceptance Letter for Azalea Extension East Project electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company.
02/27/2014 Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB
02/26/2014 Proof of Pub Azalea 138k V Extension East Project -CArrollton Free Press Standard electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company
02/26/2014 Proof of Pub Azalea 138k V Extension East Project-Dover-Times Reporter electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company
02/10/2014 Letter of notification concerning payment for expedited processing electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company.
02/07/2014 Letter of Notification Azalea 138 kV Extension East Project (Part 5 of 5) electronically filed by Mr. Yazen Alami on behalf of Ohio Power Company.
02/07/2014 Letter of Notification Azalea 138 kV Extension East Project (Part 4 of 5) electronically filed by Mr. Yazen Alami on behalf of Ohio Power Company
02/07/2014 Letter of Notification Azalea 138 kV Extension East Project (Part 3 of 5) electronically filed by Mr. Yazen Alami on behalf of Ohio Power Company
02/07/2014 Letter of Notification Azalea 138 kV Extension East Project (Part 2 of 5) electronically filed by Mr. Yazen Alami on behalf of Ohio Power Company.
02/07/2014 In the matter of the Letter of Notification Azalea 138 kV Extension East Project (Part 1 of 5) electronically filed by Mr. Yazen Alami on behalf of Ohio Power Company.