CASE NUMBER: 14-0099-EL-BNR
CASE DESCRIPTION: AVON-BEAVER #1 & #2 345 kV TRANSMISSION LINE STRUCTURE REPLACEMENT FOR STATE ROUTE 2 BRIDGE CONSTRUCTION
DOCUMENT SIGNED ON: 4/24/2024
DATE OF SERVICE: ________________________________________
12/24/2014 Response letter stating that construction on this project was completed on approximately October 31, 2014. filed by Jessica Thacker on behalf of FirstEnergy Service Company.
08/28/2014 Letter stating that construction on this project will begin the week of August 25, 2014 filed by J.Thacker on behalf of FirstEnergy Service Company.
02/19/2014 Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB.
01/17/2014 Construction Notice Avon-Beaver #1 & #2 345 kV Transmission Line Stracture Replacement for State Route 2 Bridge Construction
01/17/2014 In the matter of the Notice of Construction Avon-Beaver #1 & #2 345 kV Transmission Line Structure Replacement For State Route 2 Bridge Construction.