DIS - Case Record for 13-2350-EL-BNR Skip to main content
      
      
CASE NUMBER: 13-2350-EL-BNR
CASE DESCRIPTION: Beaver to Brownhelm Junction 345kV Transmission Line Temporary Transmission Line Extension Project
DOCUMENT SIGNED ON: 5/4/2024
DATE OF SERVICE: ________________________________________
12/16/2013 Report of investigation, Revised OPSB Executive Director Cover Letter electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB.
12/10/2013 Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB.
12/06/2013 Notice of mailing of notification letter to Public Officials with copies electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.
12/05/2013 Motion for partial waiver of review period for expedited construction notice and memorandum in support electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.
12/05/2013 In the matter of the Notice of Construction Beaver to Brownhelm Junction 345 kV Transmission Line Temporary Extension electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.