04/25/2014
|
Memorandum stating Staff has determined that the project has been put-in-service and the above case may be closed. |
04/25/2014
|
Case Status Form to close case. |
12/11/2013
|
Service Notice |
12/11/2013
|
Finding & Order adopting and approving the stipulation; that the project should be completed on or before December 11, 2014; that the Staff makes the final inspection and files a memorandum that the installation is completed. |
11/20/2013
|
In the matter of a request for the installation of new lights at the Northern Ohio & Western Railway Grade Crossing, DOT#509-179S, Stone Rd. in Gibsonburg, Ohio. |
|