01/13/2014
|
Letter of Notification that construction was completed on the London-Tangy 69 kV Transmission Line Project on approximately January 4, 2014, filed by Travis Turner on behalf of FirstEnergy Service Company. |
12/03/2013
|
Letter stating that construction on London-Tangy 69 kV Transmission Line Tap to Jefferson Industries Substation Project is expected to begin on approximately December 2, 2013 filed by T. Turner on behalf of FirstEnergy Service Company. |
11/20/2013
|
Proof of Publication. (Madison County) |
11/18/2013
|
Notice of Withdrawal of Motion for Partial Waiver electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
11/13/2013
|
Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. |
11/01/2013
|
Motion and memorandum in support for Partial Wavier of Time Period for Review electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
11/01/2013
|
In the matter of the application of American Transmission Systems, Incorporated for Letter of Notification. |