DIS - Case Record for 13-2163-EL-BLN Skip to main content
      
      
CASE NUMBER: 13-2163-EL-BLN
CASE DESCRIPTION: LONDON-TANGY 69 kV TRANSMISSION LINE LOOP TO JEFFERSON INDUSTRIES SUBSTATION
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
01/13/2014 Letter of Notification that construction was completed on the London-Tangy 69 kV Transmission Line Project on approximately January 4, 2014, filed by Travis Turner on behalf of FirstEnergy Service Company.
12/03/2013 Letter stating that construction on London-Tangy 69 kV Transmission Line Tap to Jefferson Industries Substation Project is expected to begin on approximately December 2, 2013 filed by T. Turner on behalf of FirstEnergy Service Company.
11/20/2013 Proof of Publication. (Madison County)
11/18/2013 Notice of Withdrawal of Motion for Partial Waiver electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
11/13/2013 Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB.
11/01/2013 Motion and memorandum in support for Partial Wavier of Time Period for Review electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
11/01/2013 In the matter of the application of American Transmission Systems, Incorporated for Letter of Notification.