12/29/2014
|
Letter of completion of project filed by T. Krauss, on behalf of FirstEnergy Service Company. |
06/03/2014
|
Notice that the Chamberlin-Mansfield 345 kV transmission line began commercial operation on May 28, 2014 filed by Ted Krauss on behalf of First Energy. |
07/10/2013
|
Supplement to the Letter of Notification filed by T. Krauss on behalf of FirstEnergy Service Company. |
07/03/2013
|
Report of investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
05/14/2013
|
Proof of publication for the County of Portage filed by R. J. Schmidt, Jr on behalf of American Transmission Systems, Inc. |
04/15/2013
|
Service notice for the Chamberlin-Mansfield 345kV Transmission Line Loop to Hanna Substation Project filed by Ted Krauss on behalf of FirstEnergy Service Company. |
04/15/2013
|
In the matter of the Letter of Notification for the Chamberlin-Mansfield 345kV Transmission Line Loop to Hanna Substation Project. |