CASE NUMBER: 12-2461-EL-BLN
CASE DESCRIPTION: AMERICAN TRANSMISSION SYSTEMS INC
DOCUMENT SIGNED ON: 4/18/2024
DATE OF SERVICE: ________________________________________
07/25/2014 Letter of Notification that project was completed approximately April 22, 2014 filed by S. Humphrys on behalf of FirstEnergy.
05/13/2013 Letter stating that construction on Delta-Swanton 138 kV Transmission Line Loop to Fulton project is expected to begin on or shortly after May 15, 2013 filed by S. Humphrys on behalf of FirstEnergy Service Company.
12/11/2012 Service Notice
11/05/2012 Staff Report Filed - Delta-Swanton.
09/12/2012 In the matter of the notification of FirstEnergy Service Company for Delta-Swanton 138 kV Transmission Line Loop to Fulton Substation Project filed by S. Humphrys.