07/17/2015
|
Case Action Form to close case effective 7/17/2015. |
07/02/2013
|
Notice of Completion Poston-Ross Section V electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. |
10/10/2012
|
OPSB Staff Investigation report and recommendation. |
09/05/2012
|
In the matter of the notice of Construction Poston-Ross 138kV Line (Reconductor/Rebuild Project Section V)" electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. |