06/15/2015
|
Memo closing case with and effective date of 6/15/2015. |
11/30/2012
|
Letter in response to the Construction Notice for Galion-Roberts 138 kV Transmission Line Tap to US Yachiyo Substation Project filed by J. Toth on behalf of FirstEnergy Service Company. |
10/01/2012
|
Staff investigation report and recommendations submitted on behalf of OPSB Staff, J. O'Dell. |
08/27/2012
|
In the matter of the application of Ohio Edison Company for Gallon-Roberts 138 kV Transmission Line Tap to the US Yachiyo Substation. |