Date Filed | Summary | Pages |
12/21/2017 | Closed Case action form closing case(s) effective 12/21/2017. - electronically filed by Sandra Coffey on behalf of Sarah Parrot, Attorney Examiner, Public Utilities Commission of Ohio | 2 |
08/05/2015 | Notice that the overall project was placed in service on approximately May 1, 2015 filed by T. Krauss on behalf of First Energy Service Company. | 1 |
04/15/2014 | Status report for the three referenced projects filed by T. Krauss on behalf of FirstEnergy Service Company. | 2 |
09/27/2013 | Notice of Acceptance of Staff Conditions and Supplement to Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 5 |
09/20/2013 | Staff Report of investigation electronically filed by Mr. Adam S. Bargar on behalf of Staff of OPSB. | 4 |
07/26/2013 | Letter of notification of a Project Update in the Harmon-Star 345 kV Transmission Line Project and Harmon-Toronto 345 kV Transmission Line Project filed by Jay Ruberto on behalf of FirstEnergy Service Company. | 1 |
07/02/2013 | Letter of notification of the application of South Canton-Star 345 KV and Burger - Cloverdale #1, #2 and #3 138 KV Transmission line extensions to and installation of the Harmon substation. | 113 |
05/17/2013 | Service Notice | 1 |
05/17/2013 | Administrative Law Judge Entry grants ATSI's request amending the case designation for this docket in accordance with finding (4). - electronically filed by Sandra Coffey on behalf of Sarah Parrot, Attorney Examiner, Public Utilities Commission of Ohio | 4 |
04/18/2013 | Request for Re-Desigination of Docket Designation Code electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 5 |
09/07/2012 | In the matter of the letter of notification application - Harmon Transmission substation Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 3 |