07/25/2014
|
Correspondence that the Hayes Substation Project was placed in service and construction completed May 15, 2014 filed by S. Humphrys on behalf of FirstEnergy. |
12/17/2013
|
Response regarding Condition 10: Residential Landscape Plan, filed by S. Humphrys on behalf of FirstEnergy Service Company. |
05/09/2013
|
Letter notifying the Commission as discussed at the May 6, 2013 pre-construction meeting, construction on this Project will commence as early as May 7, 2013 filed by S. M. Humphrys on behalf of FirstEnergy Service Company. |
04/01/2013
|
Notification to the PUCO Staff that the construction on this Project commenced on January 14, 2013. We will notify you once the project has been completed and placed in service filed by Scott M. Humphrys on behalf of FirstEnergy Services Company. |
03/15/2013
|
Report regarding the Hayes Substation Certificate Condition # 20, filed by S. Humphrys on behalf of FirstEnergy. |
12/18/2012
|
Service Notice |
12/17/2012
|
Opinion and Order that the November 15, 2012, Stipulation is approved and adopted. It is, further, ordered, that a certificate be issued to ATSI for the construction, operation, and maintenance of the Hayes substation subject to the 20 conditions set forth in the Stipulation and this order. |
12/07/2012
|
Continued Exhibit filing for hearing held on 11/20/12 before Hearing Examiner Daniel E. Fullin, (Part 2 of 2) |
12/07/2012
|
Exhibit filing for hearing held on 11/20/12 before Hearing Examiner Daniel E. Fullin, (Part 1 of 2) |
12/06/2012
|
Transcript of American Transmission Systems, Inc. hearing held on 11/20/12. electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Guzzo, Deborah Mrs. |
11/29/2012
|
Proof of Pub of Erie County electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
11/21/2012
|
Transcript of American Transmission Systems, Inc. hearing held before Dan Fullin, Administrative Law Judge, on 11/08/12 at the BGSU Firelands College, Cedar Point 13 Center, One University Drive, Huron, Ohio electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. |
11/16/2012
|
Testimony of Scott Humphrys electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated. |
11/15/2012
|
Joint Stipulation and Recommended Findings of Fact and Conclusions of Law electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated |
11/08/2012
|
Motion for order accepting proof of publication of second public notice of public and evidentiary hearings and memorandum in support electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |
10/30/2012
|
Notice of Prehearing Statement of Issues electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated |
10/24/2012
|
Service Notice |
10/24/2012
|
Staff Report Filed electronically filed by Mr. James S. O'Dell on behalf of Staff of OPSB. |
10/12/2012
|
Affidavit of Proof of Mailing of Notification Letters electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
10/05/2012
|
Proof of Publication. (Erie County) |
09/18/2012
|
Notice that the required application fee for the Hayes Project has been paid filed by S. Humphrys on behalf of FirstEnergy Service Company. |
09/14/2012
|
Service Notice |
09/14/2012
|
Entry by Administrative Law Judge ordering that applicant's waiver requests be granted and establishing the procedural schedule to be followed in this case. - electronically filed by Sandra Coffey on behalf of Daniel Fullin, Attorney Examiner, Public Utilities Commission of Ohio |
09/14/2012
|
Affidavit of Proof of Service of complete application on public officers, electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
09/14/2012
|
Letter of Notification filed by John H. Jones, Assistant Attorney General, on behalf of the Staff of the Ohio Power Siting Board stating that Staff does not object to the waivers requested by applicant in its June 1, 2012 and August 9, 2012 motions for certain waivers. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board. |
09/11/2012
|
Letter of compliance to Morgan Parke, ATSI from T. Snitchler, OPSB Staff. |
08/17/2012
|
Application for a Certificate of Environmental Compatibility and Public Need for the Hayes Substation Project filed by S. Humphreys on behalf of ATSI. |
08/15/2012
|
Amendment to Motion for Waiver electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated. |
08/09/2012
|
Motion For Waiver and Memorandum in Support electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated |
07/31/2012
|
Application For A Certificate of Environmental Compatibility and Public Need - Hayes Substation Project filed by Scott Humphrys on behalf of FirstEnergy Service Company. |
06/01/2012
|
Motion for Certain Waivers and Memorandum in Support electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
08/15/2011
|
In the matter of the pre-application notification of Hayes Substation Project filed on behalf of FirstEnergy Service Company by S. Humphrys. |