CASE NUMBER: 11-4711-EL-BSB
CASE DESCRIPTION: FIRST ENERGY
DOCUMENT SIGNED ON: 9/20/2024
DATE OF SERVICE: ________________________________________
07/25/2014 Correspondence that the Hayes Substation Project was placed in service and construction completed May 15, 2014 filed by S. Humphrys on behalf of FirstEnergy.
12/17/2013 Response regarding Condition 10: Residential Landscape Plan, filed by S. Humphrys on behalf of FirstEnergy Service Company.
05/09/2013 Letter notifying the Commission as discussed at the May 6, 2013 pre-construction meeting, construction on this Project will commence as early as May 7, 2013 filed by S. M. Humphrys on behalf of FirstEnergy Service Company.
04/01/2013 Notification to the PUCO Staff that the construction on this Project commenced on January 14, 2013. We will notify you once the project has been completed and placed in service filed by Scott M. Humphrys on behalf of FirstEnergy Services Company.
03/15/2013 Report regarding the Hayes Substation Certificate Condition # 20, filed by S. Humphrys on behalf of FirstEnergy.
12/18/2012 Service Notice
12/17/2012 Opinion and Order that the November 15, 2012, Stipulation is approved and adopted. It is, further, ordered, that a certificate be issued to ATSI for the construction, operation, and maintenance of the Hayes substation subject to the 20 conditions set forth in the Stipulation and this order.
12/07/2012 Continued Exhibit filing for hearing held on 11/20/12 before Hearing Examiner Daniel E. Fullin, (Part 2 of 2)
12/07/2012 Exhibit filing for hearing held on 11/20/12 before Hearing Examiner Daniel E. Fullin, (Part 1 of 2)
12/06/2012 Transcript of American Transmission Systems, Inc. hearing held on 11/20/12. electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Guzzo, Deborah Mrs.
11/29/2012 Proof of Pub of Erie County electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
11/21/2012 Transcript of American Transmission Systems, Inc. hearing held before Dan Fullin, Administrative Law Judge, on 11/08/12 at the BGSU Firelands College, Cedar Point 13 Center, One University Drive, Huron, Ohio electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc.
11/16/2012 Testimony of Scott Humphrys electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated.
11/15/2012 Joint Stipulation and Recommended Findings of Fact and Conclusions of Law electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated
11/08/2012 Motion for order accepting proof of publication of second public notice of public and evidentiary hearings and memorandum in support electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.
10/30/2012 Notice of Prehearing Statement of Issues electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated
10/24/2012 Service Notice
10/24/2012 Staff Report Filed electronically filed by Mr. James S. O'Dell on behalf of Staff of OPSB.
10/12/2012 Affidavit of Proof of Mailing of Notification Letters electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
10/05/2012 Proof of Publication. (Erie County)
09/18/2012 Notice that the required application fee for the Hayes Project has been paid filed by S. Humphrys on behalf of FirstEnergy Service Company.
09/14/2012 Service Notice
09/14/2012 Entry by Administrative Law Judge ordering that applicant's waiver requests be granted and establishing the procedural schedule to be followed in this case. - electronically filed by Sandra Coffey on behalf of Daniel Fullin, Attorney Examiner, Public Utilities Commission of Ohio
09/14/2012 Affidavit of Proof of Service of complete application on public officers, electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
09/14/2012 Letter of Notification filed by John H. Jones, Assistant Attorney General, on behalf of the Staff of the Ohio Power Siting Board stating that Staff does not object to the waivers requested by applicant in its June 1, 2012 and August 9, 2012 motions for certain waivers. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board.
09/11/2012 Letter of compliance to Morgan Parke, ATSI from T. Snitchler, OPSB Staff.
08/17/2012 Application for a Certificate of Environmental Compatibility and Public Need for the Hayes Substation Project filed by S. Humphreys on behalf of ATSI.
08/15/2012 Amendment to Motion for Waiver electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated.
08/09/2012 Motion For Waiver and Memorandum in Support electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated
07/31/2012 Application For A Certificate of Environmental Compatibility and Public Need - Hayes Substation Project filed by Scott Humphrys on behalf of FirstEnergy Service Company.
06/01/2012 Motion for Certain Waivers and Memorandum in Support electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
08/15/2011 In the matter of the pre-application notification of Hayes Substation Project filed on behalf of FirstEnergy Service Company by S. Humphrys.