DIS - Case Record for 10-0712-EL-GAG Skip to main content
      
      
CASE NUMBER: 10-0712-EL-GAG
CASE DESCRIPTION: BOARD OF ERIE COUNTY COMMISSIONERS
DOCUMENT SIGNED ON: 4/30/2024
DATE OF SERVICE: ________________________________________
04/29/2024 Certificate No. 10-218E issued.
03/29/2024 In the Matter of the Application of Board of Erie County Commissioners.
03/04/2024 Opt-Out Notice electronically filed by Ms. Chelsea M. Baglia on behalf of Energy Harbor and Erie County.
12/15/2023 Notice of Resolution Authorizing The Erie County Commissioners to act as Purchasing Agent and Governmental Aggregator for Natural Gas and Electric Supply filed by Andrea Flowers on behalf of The Village of Berlin Heights. (FAX)
10/06/2023 Opt-Out Notice electronically filed by Ty Brocksieker on behalf of Energy Harbor and Erie County.
07/05/2023 Notice from the Village of Castalia to Cede Authority to Erie County for Electric Power Supply Services filed by Andrea Flowers on behalf of the Village of Castalia. (FAX)
05/05/2022 Certificate No. 10-218E issued.
04/04/2022 In the Matter of the Application of Board of Erie County Commissioners.
06/10/2021 Opt-Out Notice for Board of Erie County Commissioners electronically filed by Mr. David F. Proano on behalf of Dynegy Energy Services (East), LLC.
01/07/2021 Opt-Out Notice for the Board of Erie County Commissioners electronically filed by Miss Shannon McCulloch on behalf of AEP Energy, Inc.
07/27/2020 Renewal Certificate # 10-218E issued electronically filed by Mr. Brandon J. Jenkins on behalf of PUCO Staff.
06/17/2020 Service Notice
06/17/2020 Finding & Order approving the applications in the above-captioned proceedings for certification as competitive retail electric service providers. electronically filed by Ms. Mary E Fischer on behalf of Public Utilities Commission of Ohio.
06/08/2020 Opt-Out Notice for the Board of Erie County Commissioners electronically filed by Miss Shannon McCulloch on behalf of AEP Energy, Inc.
05/18/2020 Amended Exhibit A-2 filed by A. Flowers on behalf of Board of Erie County Commissioners.
05/18/2020 Staff Review and Recommendation electronically filed by Nedra Ramsey on behalf of PUCO Staff.
05/07/2020 Renewal Application of Board of Erie County Commissioners for continued Certification as an Electric Governmental Aggregator filed by M. Frye.
12/13/2019 Opt-Out Notice for the Board of Erie County Commissioners electronically filed by Miss Shannon McCulloch on behalf of AEP Energy, Inc.
11/04/2019 Notice of material change filed by A. Flowers on behalf of Erie County Commissioners.
06/21/2019 Opt-Out Notice for the Board of Erie County Commissioners electronically filed by Miss Shannon McCulloch on behalf of AEP Energy, Inc.
06/29/2018 Renewal Certificate # 10-218E(5) issued.
06/14/2018 Opt-Out Notice to be sent to newly eligible customers in the County's electric aggregation program electronically filed by Mark R Burns on behalf of Erie County.
05/17/2018 Renewal Application of Board of Erie County Commissioners for certification as an Electric Governmental Aggregator electronically filed by Mark R. Burns.
09/06/2017 Opt-Out Notice to be sent to newly eligible customers in the County's electric aggregation program electronically filed by MARK R BURNS on behalf of Erie County.
08/03/2016 Renewal Certificate No.10-218E (4) issued.
05/27/2016 Opt-Out Notice to be sent to newly eligible customers in the County's electric aggregation program electronically filed by Mark R. Burns on behalf of Erie County.
05/04/2016 Renewal Application for certification as a governmental aggregator of electricity electronically filed by MARK R BURNS on behalf of Erie County.
04/27/2016 Opt-Out Notice renewal mailing to be sent to customers in the County's electric aggregation program electronically filed by MARK R BURNS on behalf of Erie County.
11/07/2014 Opt-Out Notice to be sent to current customers in the Erie County's electric aggregation program. electronically filed by MARK R BURNS on behalf of Erie County.
08/14/2014 Opt-Out Notice to be sent to newly eligible customers in the County's electric program electronically filed by MARK R BURNS on behalf of Erie County.
06/09/2014 Renewal Certificate # 10-218E(3) issued.
05/22/2014 Opt-Out Notice to be sent to newly eligible customers in the County's Electric Aggregation Program. electronically filed by MARK R BURNS on behalf of Erie County.
05/09/2014 Renewal Application for certification renewal as a governmental aggregator of electric of Erie County. electronically filed by MARK R BURNS on behalf of Erie County
02/19/2014 Opt-Out Notice to be sent to newly eligible customers in the County's Electric Aggregation Program. electronically filed by MARK R BURNS on behalf of Erie County.
10/04/2013 Opt-Out Notice to be sent to newly eligible customers in the County's Electric Aggregation Program. electronically filed by MARK R BURNS on behalf of Erie County.
08/16/2013 Opt-Out Notice to be sent to newly eligible customers in the County's electric aggregation program. electronically filed by Mark R. Burns on behalf of Erie County.
06/13/2013 Opt-Out Notice to be sent to newly eligible customers in the County's Electric Aggregation Program electronically filed by Mark R. Burns on behalf of Erie County .
04/19/2013 Opt-Out Notices being sent to customers in the Erie County's Electric Aggregation Program. electronically filed by Mark R. Burns on behalf of Erie County.
12/03/2012 Supplemental opt-out notices being sent to newly eligible residents and small businesses electronically filed by MARK R BURNS on behalf of Erie County
06/25/2012 Certificate No. 10-218E (2) issued.
06/01/2012 Opt-Out Notices being sent to residential and commercial accounts in the Erie County Electric Aggregation Program electronically filed by MARK R BURNS on behalf of Erie County.
05/14/2012 Renewal application for certification as a governmental aggregator of electric, electronically filed by MARK R BURNS on behalf of Board of Erie County Commissioners.
01/23/2012 Supplemental Opt-Out notices sent to residential and commercial accounts in the Erie County Electric Aggregation Program filed by Independent Energy Consultants, electronically filed by MARK R BURNS on behalf of Erie County.
09/15/2011 Opt-Out Notices of Erie County filed by M. Burns
02/24/2011 Opt-out notice for Erie County, filed by M. Burns.
08/10/2010 Opt out notification for Erie County electric aggregation program being sent to residential and commercial accounts on or after August 19, 2010 and scheduled to end on or after September 9, 2010 filed by M. Burns.
08/09/2010 Opt out notification to be sent on or after August 19, 2010 and scheduled to end September 9, 2010 filed on behalf of Erie County by M. Burns. (FAX)
06/29/2010 Certificate No.10-218E (1) issued.
05/25/2010 In the matter of the application of the Board of Erie County Commissioners for certification for governmental aggregators.