12/15/2011
|
Case Status Form, Closed effective 12/15/2011. |
12/15/2011
|
Final Report for the grade crossing project in Tuscarawas County, Auburn Township at Yoder Rd. filed by S. Zurfley on behalf of the PUCO staff. |
09/29/2011
|
Memo stating that construction was not completed by deadline, September 26, 2011, and that on September 29,2011, PUCO Staff, Mr. Zurfley reported that the crossing was put in service the afternoon of Wednesday, September 28, 2011 and stated that the contractor will return to the site to replace the correct train detection unit
when it is available filed by PUCO Rail Staff, J. Henry. |
09/27/2011
|
PUCO/FRA field investigator Shawn Zurfiey visited the project site on Tuesday September 27, 2011 and found that OHCR has failed to meet the construction deadline of September 26, 2011. |
09/20/2011
|
Service Notice |
09/20/2011
|
Entry ordering OCR's request for an extension of time is denied and that OCR proceed with and complete the project. |
09/19/2011
|
PUCO Staff does not recommend the 30 day extension for the Yoder Road Project. |
09/19/2011
|
Request to modify due date for project 10-480-RR-STP filed by Alan Klodell on behalf of Attorney General's Transportation Section. |
09/16/2011
|
Request for Extension for the Grade Crossing Project/ Yoder Road filed by Daniel Birrell on behalf of Ohio Central Railroad.(FAX) |
09/09/2011
|
Request for project extension of installation at Yoder Rd., Auburn Township for AEP to finish the installation of the pole line, filed by D. Birrell. |
09/09/2011
|
Memo from Staff that they do not recommend the extension of time requested by OHCR on September 9, 2011. |
07/15/2011
|
Service Notice |
07/15/2011
|
Entry ordering that OCR's request for an extension of time be granted; that OCR complete the installation of active warning devices at the Yoder Road grade crossing (DOT#474-256M), in Auburn Township, Tuscarawas County by September 26, 2011. |
07/06/2011
|
Request of Ohio Central Railroad for an additional 90 day extension filed by D. Birrell on behalf of the Ohio Central Railroad Company, Incorporated. |
07/06/2011
|
Response recommending the request of Ohio Central Railroad for a 90 day extension of the project deadline until September 26, 2011, filed by Staff, J. Henry. |
05/27/2011
|
Service Notice |
05/26/2011
|
Request by Ohio Central Railroad Company, Inc. for an additional 90 day extension filed by D. Birrell on behalf of Ohio Central Railroad Company, Incorporated. |
05/25/2011
|
Service Notice |
05/25/2011
|
Entry that OCR's request for an extension of time to complete the
installation of this project be granted, as set forth in Finding 6 and that OCR complete the installation of active warning devices at Yoder Road (DOT#474-256M) in Auburn Township, Tuscarawas County by June 28, 2011. (SEF) |
05/24/2011
|
Memorandum stating staff recommends that the Commission grant a 90 day extension to August 26, 2011 for Ohio Central Railroad Company, Incorporated. |
05/24/2011
|
Request from Ohio Central Railroad Company, Inc. for an additional 90 day extension filed by D. Birrell on behalf of Ohio Central Railroad Company, Inc. |
04/27/2011
|
Service Notice |
04/27/2011
|
Entry ordering that OCR's request for an extension of time to complete the installation of this project be granted, as set forth in Findings (4) and (5). (SEF) |
04/19/2011
|
Memorandum granting Ohio Central Railroad's request for a 30 day extension filed by J. Henry. |
04/14/2011
|
Ohio Central Railroad Incorporated requests a 60 day extension due to adjacent property owners refusing to allow the electric service provider, Frontier Power, access/ easement across their property for the routing of electrical power to the site filed by D. Birrell. |
09/15/2010
|
Authorization of Ohio Central Railroad to proceed with field construction for the referenced project, filed by J. Henry on behalf of PUCO Rail Division. |
08/06/2010
|
Status report for the Ohio Central Railroad grade crossing/ Yoder Road, Auburn Twp project filed by D. Birrell, signal supervisor. |
08/02/2010
|
Service Notice |
08/02/2010
|
Entry ordering that OCR's request for extension of time to file site plans and cost estimates for this project be granted. (KKS) |
07/29/2010
|
Letter stating that due to circumstances beyond their control, the plans and estimates have been delayed until August 6, 2010 filed by D. Birrell on behalf of The Ohio Central Railroad System. |
07/28/2010
|
Letter informing the Commission that there has been a delay in receiving estimates from the designated contractor filed by D. Birrell. (FAX) |
04/28/2010
|
Service Notice |
04/28/2010
|
Finding and order ordering that the stipulation is adopted and approved. |
04/15/2010
|
In the matter of a request for the installation of active warning devices for Ohio Central Railroad Grade Crossing, DOT#474-256M, on Yoder Road in Auburn Township, Tuscarawas County. |