CASE NUMBER: 09-0552-EL-BLN
CASE DESCRIPTION: THE CITY OF HAMILTON ELECTRIC DEPARTMENT PROPOSED SUBSTATION NO 4 TO SUBSTATION NO 13 138 KV TRANSMISSION LINE PROJECT
DOCUMENT SIGNED ON: 4/23/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
04/26/2012 Notice that the City of Hamilton has completed construction and energized Substations No. 4, 13, and 10, filed by Randy Meyer.
07/12/2010 Memo stating construction of the 138-kV transmission line has been completed, filed by A. McIntire on behalf of the City of Hamilton.
08/25/2009 Staff investigation report and recommendation filed on behalf of Staff of the Public Utilities Commission of Ohio.
08/24/2009 Letter of notification regarding the City of Hamilton Substation No. 4 to Substation No. 13 138 kV Transmission Line filed by R. Meyer on behalf of the City of Hamilton.
07/29/2009 Supplement to the City of Hamilton's Substation No. 4 to Substation No. 13 138 kV Transmission line letter of notification application, Kirtland Snake and Eastern Box Turtle Presence / Absence Survey Final Report filed by R. Meyer on behalf of the City of Hamilton.
06/30/2009 Application continued. (Part 2 of 2)
06/30/2009 In the matter of the notification to Ohio Power Siting Board of the City of Hamilton Electric Department proposed substation No. 4 to substation No. 13 138 kV Transmission Line Project. (Part 1 of 2)