Case Title: THE CITY OF HAMILTON ELECTRIC DEPARTMENT PROPOSED SUBSTATION NO 4 TO SUBSTATION NO 13 138 KV TRANSMISSION LINE PROJECT
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BLN-letter of notification
Date Opened: 6/30/2009
Date Closed: 3/20/2015
Printable Docket Card Service List
View All
1 - 8 of 8 documents 1 /  1 
Date FiledSummaryPages
03/20/2015Case Action Form to Close Cases effective 3/20/2015.6
04/26/2012Notice that the City of Hamilton has completed construction and energized Substations No. 4, 13, and 10, filed by Randy Meyer.1
07/12/2010Memo stating construction of the 138-kV transmission line has been completed, filed by A. McIntire on behalf of the City of Hamilton. 1
08/25/2009Staff investigation report and recommendation filed on behalf of Staff of the Public Utilities Commission of Ohio.2
08/24/2009Letter of notification regarding the City of Hamilton Substation No. 4 to Substation No. 13 138 kV Transmission Line filed by R. Meyer on behalf of the City of Hamilton.3
07/29/2009Supplement to the City of Hamilton's Substation No. 4 to Substation No. 13 138 kV Transmission line letter of notification application, Kirtland Snake and Eastern Box Turtle Presence / Absence Survey Final Report filed by R. Meyer on behalf of the City of Hamilton.13
06/30/2009Application continued. (Part 2 of 2)176
06/30/2009In the matter of the notification to Ohio Power Siting Board of the City of Hamilton Electric Department proposed substation No. 4 to substation No. 13 138 kV Transmission Line Project. (Part 1 of 2)172
 