03/20/2015
|
Case Action Form to Close Cases effective 3/20/2015. |
12/11/2009
|
Letter of notification that construction for the Bluebell-Highland 138 kV Transmission Line Tap to Republic Special Metals was completed on approximately November 13, 2009 filed by S. Humphrys on behalf of First Energy Service Company. |
12/07/2009
|
Letter of notification that construction for the Bluebell-Highland 138 kV Transmission Line Tap to Republic Special Metals was completed on approximately November 13, 2009 filed by S. Humphrys on behalf of First Energy Service Company. |
05/07/2009
|
Staff investigation report and recommendation filed by PUCO. |
03/13/2009
|
In the matter of the letter of notification of the Ohio Edison Company and American Transmission Systems, Incorporated for the project for Bluebell-Highland 138kV transmission line tap to Republic Special Metals in Jackson Township, Mahoning County. |