DIS - Case Record for 08-1203-EL-CSS Skip to main content

Case Record For:

08-1203-EL-CSS

File a Public Comment
Case Title: MRS SUSAN AIKEY WALKER VS OHIO EDISON AND FIRST ENERGY
Status: AR-Archived
Industry Code: EL-ELECTRIC
Purpose Code: CSS-Complaint on service or safety
Date Opened: 11/3/2008
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
01/22/2013Case action form archiving case with an effective date of 1/22/13.1
04/26/2012Case action form to Close case effective 04/26/2012.1
01/18/2012Service notice.2
01/18/2012Opinion and order that the complaint be dismissed.11
08/25/2010Service Notice2
08/25/2010Entry ordering that this proceeding is suspended pending resolution of the issues.4
07/09/2009Exhibits for transcript electronically filed 07/08/09.40
07/08/2009Transcript of Susan Aikey-Walker, Ohio Edison for hearing held on 6/23/09, before D. Jennings, hearing examiner. Electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Gibson, Karen Sue Mrs.159
06/17/2009Testimony of Kimberly K. Vujas filed by E. Miller on behalf of Ohio Edison Company.8
06/16/2009Direct expert testimony of Kimberly K. Vujas filed on behalf of Ohio Edison Company by E. Miller. (FAX)8
06/10/2009Service Notice.1
06/10/2009Entry ordering a hearing be rescheduled to begin on June 23, 2009, at 10:00 a.m. in hearing room 11-G, at the offices of the Commission, 180 East Broad Street, Columbus, Oh 43215; expert testimony be filed on or before June 16, 2009. (LDJ)2
06/04/2009Motion for extension of time and continuance and request for expedited ruling and memorandum in support filed by E. Miller on behalf of Ohio Edison Company. 5
06/03/2009Motion for extension of time and continuance and request for expedited ruling and memorandum in support filed by E. Miller on behalf of FirstEnergy Service Company. (FAX)6
04/28/2009Service Notice1
04/27/2009Entry ordering that a hearing shall begin on June 16, 2009, at 10:00 a.m., in Hearing Room 11-G, at the offices of the Commission, 180 East Broad Street, Columbus, Ohio 43215. LDJ2
02/20/2009Service notice.1
02/20/2009Entry ordering the prehearing settlement conference scheduled for Wednesday, February 25, 2009, at 2:00 p,m. shall be conducted in person at the offices of the Commission, 180 East Broad Street, Columbus, Ohio in Hearing Room 11-B.(LDJ)2
02/05/2009Service Notice1
02/05/2009Entry ordered that a prehearing settlement conference be held by telephone on Thursday, February 25, 2009, at 2:00 P.M. (LDJ)3
12/11/2008Response to Ohio Edison's reply filed by S. Walker, complainant. (FAX)11
11/25/2008Answer and motion to dismiss of the Ohio Edison Company filed by E. Miller. (original)4
11/24/2008Answer and motion to dismiss of the Ohio Edison Company filed by E. Miller. (FAX)5
11/04/2008Complaint service letter and copy of complaint sent to: Ohio Edison/FirstEnergy Company.1
11/04/2008Complaint response letter and brochure sent to: Susan Aikey Walker.1
11/03/2008In the matter of the complaint of S. Walker vs. Ohio Edison & First Energy for the alleged unjust billing practices. 24