06/03/2010 Letter stating that Dominion has completed, on May 28, 2010, the installation of the gas facilities as detailed in this case filed by J. Schniegenberg.
12/24/2009 Notification for start of construction on Fremont Energy Center project, filed by J. Schniegenberg on behalf of Dominion East Ohio.
06/12/2008 Investigation report and recommendation filed by PUCO Staff.
05/20/2008 In the matter of the construction notice of Dominion East Ohio Gas for the proposed natural gas transmission line for the Fremont Energy Center.