DIS - Case Record for 07-0771-RR-FED Skip to main content
      
      
CASE NUMBER: 07-0771-RR-FED
CASE DESCRIPTION: WHEELING & LAKE ERIE RAILWAY
DOCUMENT SIGNED ON: 5/22/2024
DATE OF SERVICE: ________________________________________
07/25/2008 Memo closing case with an effective date of 7/25/08.
07/10/2008 Service Notice
07/10/2008 Entry ordered that an extension to time to complete the project be granted ; that the Mogadore Road project be completed by July 25, 2008. (SF)
07/09/2008 Letter of a formal request to extend the installation deadline up to 30-days to allow for a delay in electric service connection filed by D. Reinsel on behalf of Wheeling & Lake Erie Railway Company.
07/09/2008 Memo stating that Wheeling & Lake Railway filed in this docket a request for a 30-day extension of time to complete the installation of the grade crossing project at Portage County, near Brimfield, Mogadore Road, DOT#472-651P, filed by G. Martin, PUCO staff.
07/11/2007 Service Notice
07/11/2007 Entry ordering that W&LE submit to the Commission and ORDC site plans and cost estimates for the project by October 11, 2007; that by October 18, 2007, a letter be filed in this docket advising that site plans and cost estimates have been submitted; that the project should be completed by July 11, 2008.
06/29/2007 In the matter of the application for authorization of the Wheeling & Lake Erie Railway to install an active grade crossing warning device in Portage County.