Date Filed | Summary | Pages |
03/21/2005 | Correspondence stating that construction will not begin in February, 2005, however that the contractor will mobilize on or about Monday, March 7, 2005 with construction beginning during the period March 16-21, 2005 filed by C. Schraff on behalf of Buckeye Gulf Coast Pipelines, LP. | 2 |
03/02/2005 | Correspondence stating that BuckeyeGulf coast Pipelines, LP did not initiate construction of the project during February, 2005, that its contractor will commence construction during the period of March 16-21, 2005 filed by C. Schraff. | 2 |
01/10/2005 | Service Notice | 1 |
01/10/2005 | Entry approving Buckeye Gulf Coast Pipe Lines, L.P. September 30, 2004 application as set forth in this decision. Buckeye may commence construction of this approve project immediately. If construction will not begin in February 2005, Buckeye shall file a notice in this docket of the new start date. | 6 |
12/08/2004 | Staff Investigation Report and Recommendation. | 4 |
11/12/2004 | Entry ordering that the approval of this application is suspended. (GP) | 3 |
11/12/2004 | Service Notice | 1 |
09/30/2004 | In the matter of the letter of notification of Buckeye Gulf Coast Pipe Lines, LP for the Sunoco to BP Hydrogen Pipeline, Lucas County. | 53 |
|