CASE NUMBER: 04-0057-EL-BLN
CASE DESCRIPTION: FIRSTENERGY CORPORATION
DOCUMENT SIGNED ON: 9/20/2024
DATE OF SERVICE: ________________________________________
06/22/2004 Letter informing Commission that project was completed on 6/7/04, filed on behalf of applicant by T. Krauss.
05/04/2004 Letter to Mr. Lambeck notifying that the start of construction was slightly delayed beyond due date, and is expected to begin on approximately May 6, 2004, notification will be made when project is completed, filed on behalf of applicant by T. Krauss.
02/24/2004 Staff investigation report and recommendation for the West Akron-West Medina #1 Transmission Line Tap to Buckeye Substation project.
01/15/2004 In the matter of the application of American Transmission Systems, Inc. to the State of Ohio Power Siting Board for the West Akron-West Medina #1, 138kV Transmission Line Tap to Buckeye Substation.