05/27/2004
|
Letter notifying Commission that project was completed and line re-energized on May 12, 2004, filed on behalf of applicant by R. McElfresh. |
09/16/2003
|
Letter informing the Commission that applicant wishes to begin construction no later than September 16, 2003, filed by R. McElfresh. |
09/09/2003
|
Letter in response to Construction Notice, filed by K. Lambeck, PUCO staff. |
09/08/2003
|
Investigation report approving the construction notice, filed by J. O'Dell, PUCO staff. |
08/06/2003
|
In the matter of Cincinnati Gas & Electric Company construction notice to relocate approximately 42 poles along the subject transmission line. |
|