DIS - Case Record for 02-3256-GA-BTA Skip to main content
      
      
CASE NUMBER: 02-3256-GA-BTA
CASE DESCRIPTION: CINCINNATI GAS & ELECTRIC COMPANY
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
07/07/2003 Service notice filed.
07/07/2003 Ordered that the certificate of environmental compatibility and public need for the 01-520 natural gas transmission pipeline is hereby amended to permit the three relocations of the pipeline, as described in this order, subject to the conditions set forth in 01-520. The certificate conditions are hereby amended to incorporate the three requested new locations.
05/21/2003 Proof of publication (Clinton) County, State of Ohio filed by M. Pahutski.
04/24/2003 Amended application to include the Certificate of Service along with the proof of pubs. for Hamilton, Clermont, Warren, Butler, Brown, Adams and Highland Counties, filed on behalf of Cinergy by M. Pahutski.
03/31/2003 Letter regarding construction drawings filed on behalf of applicant by R. McElfresh.
03/25/2003 Service Notice.
03/24/2003 Entry ordering that CG&E serve copies of the amendment application and give public notice in accordance with Finding 4. (SL)
03/06/2003 Investigative report approving application filed by J.O'Dell and R. Strom.
03/06/2003 Investigation report by staff member R. Strom.
02/14/2003 Reports filed on behalf of applicant by R. McElfresh.
01/13/2003 Corrected cover page for the C-314 Natural Gas Pipeline Project application to amend the certificate, filed on behalf of Cinergy by R. McElfresh.
01/12/2003 Amended cover page for C-314 application to amend the certificate, filed on behalf of The Cincinnati Gas & Electric Company by R. McElfresh.
12/13/2002 In the matter of the application of The Cincinnati Gas & Electric Company to amend the certificate of environmental compatibility and public need for the C314 Natural Gas Transmission Pipeline in Butler, Warren and Hamilton Counties.