Date Filed | Summary | Pages |
09/13/2002 | Service Notice. | 1 |
09/12/2002 | Entry ordering that EA's September 5, 2002 request for an expedited ruling is granted; that EA's request for clarification of the Commission's September 5, 2002 ruling is modified to allow any of the acquired customer contracts that do not have extension/renewal clauses (or for which EA cannot determine contain extension/renewal clauses) to be extended up to December 1, 2002. | 2 |
09/06/2002 | Motion for clarification and motion for an expedited ruling and memorandum in support filed on behalf of applicant by J. Migden. | 4 |
09/05/2002 | Entry approving the application; that EA's request for an expedited ruling is granted. | 3 |
09/05/2002 | Service Notice. | 1 |
08/27/2002 | In the matter of the application of Energy America, LLC for a waiver of Section 4901:1-29-10(F) Ohio Administrative Code. | 4 |