09/02/2003
|
Memo stating that the grade crossing upgrade has been completed and placed in service and requesting that this case be closed of record, filed by G. Martin, PUCO staff. |
07/17/2003
|
Request for extension of time, filed on behalf of CSX Transportation by P. Carine. |
07/15/2003
|
Service notice filed. |
07/15/2003
|
Entry ordering that CSX's request for an extension of time to complete the project be granted and CSX complete the project by August 18, 2003. (APA) |
07/11/2003
|
Letter requesting a 30-day extension of the ordered construction due date of July 18, 2003, on behalf of CSX Transportation, filed by P. Carine. |
07/11/2003
|
Memo recommends the request of 30 days extension be granted, by staff G. Martin. |
07/18/2002
|
Entry ordering that CSX submit site plans and cost estimates for the projects within 90 days of the date of this entry; that CSX proceed with construction of the projects, to be completed by July 18, 2003. |
07/18/2002
|
Service Notice. |
06/27/2002
|
In the matter of the Subsidy Agreement between the City of Van Wert, CSX, PUCO, and ORDC. |