01/24/2003 | Letter informing the Ohio Power Siting Board that on October 15, 2002, the 12 inch pipeline installed for the East Broad Street Betterment project was placed "In Service", filed on behalf of Columbia Gas of Ohio by M. Sucharski. | 1 |
07/16/2002 | Letter stating that the planned date of construction activity is to begin on or thereafter July 15, 2002, filed on behalf of applicant by M. Sucharski. | 1 |
07/09/2002 | Letter stating that the planned construction activity is to begin on or thereafter July 15, 2002, filed on behalf of applicant by M. Sucharski. | 1 |
06/18/2002 | Response letter regarding the construction notice project filed by K. Lameck | 2 |
06/17/2002 | Investigation report construction notice project name East Broad Street Betterment, Company Columbia Gas of Ohio, Inc., by staff L. Winget, E. Smith and S. Mallone. | 1 |
06/05/2002 | In the matter of Columbia Gas of Ohio Inc. submits the construction notice concerning a proposed pipeline replacement known as the East Broad Street Betterment project. | 19 |