04/02/2003
|
Memo requesting that these cases be closed of record, filed by G. Martin, PUCO staff. |
03/15/2002
|
Service Notice. |
03/14/2002
|
Entry ordering that TLE&W submit site plans and cost estimates for the project within 90 days of the date of this entry; that TLE&W proceed with construction of the project, to be completed by March 14, 2003. |
03/04/2002
|
In the matter of the authorization of the Toledo, Lake Erie & Western Railway to proceed with construction of an active grade crossing warning device in Lucas County. |
|