DIS - Case Record for 02-0046-EL-CSS Skip to main content
      
      
CASE NUMBER: 02-0046-EL-CSS
CASE DESCRIPTION: BRIAN TOMLIN VS COLUMBUS SOUTHERN POWER COMPANY & AMERICAN ELECTRIC POWER COMPANY, INC.
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
06/03/2003 Letter stating that Columbus Southern Power Co. filed a notice of dismissal in Ohio Supreme Court Case No. 03-0656 and that CSP does not accept the Commission's decision or believes it to be lawful, filed by R. Evans.
05/12/2003 Supreme Court Transmittal Papers.
04/11/2003 Notice of appeal of Appellant Columbus Southern Power Company filed by R. Evans.
03/26/2003 Notice of withdrawal of application for rehearing, filed on behalf of complainant by B. Royer and D. Moore, Jr.
03/25/2003 Entry denying CSP's application for rehearing.
03/20/2003 Memorandum contra complainants application for rehearing filed on behalf of Columbus Southern Power Company by R. Evans.
03/13/2003 Application for rehearing filed on behalf of complainants by B. Royer.
02/11/2003 Entry ordering that CSP's application for rehearing is granted for the limited purpose of allowing the Commission additional time in which to consider the issues raised on rehearing.
02/11/2003 Service Notice
01/23/2003 Memorandum contra to Columbus Southern Power Company's application for rehearing filed on behalf of complainants by B. Royer and D. Moore, Jr.
01/13/2003 Application for rehearing of the Commission's December 12, 2002 Opinion and Order, filed on behalf of Columbus Southern Power Company by R. Evans.
12/12/2002 Opinion & Order granting, in part, and denying, in part, the complainant's request for a finding that CSP failed to adequately maintain, inspect and repair its facilities in violation of the NESC's
12/12/2002 Service Notice.
11/14/2002 Reply filed on behalf of complainant by D. Moore, Jr. and B. Royer.
11/06/2002 Response to complainant's statement of additional authority, filed on behalf of respondent, Columbus Southern Power Co., by M. Resnik.
10/30/2002 Statement of additional authority filed by B. Royer.
09/18/2002 Reply filed on behalf of respondent, Columbus Southern Power Co., by R.L. Evans.
09/18/2002 Reply brief of complainants filed by B. Royer.
09/13/2002 Corrections to brief, filed on behalf of complainants by B. Royer.
09/12/2002 Initial brief filed on behalf of complainants by B. Royer and D. Moore, Jr.
09/12/2002 Post-hearing brief filed on behalf of respondent, Columbus Southern Power Co., by R.L. Evans.
09/03/2002 Transcripts continued. (Part 3 of 3)
09/03/2002 Transcripts continued. (Part 2 of 3)
09/03/2002 Transcripts filed for hearings held August 27, 2002 (Volume II) and August 28, 2002 (Volume III), PUCO-Columbus, OH. (Part 1 of 3)
08/29/2002 Transcript continued. (Part 2 of 2)
08/29/2002 Transcript filed for hearing held August 26, 2002, (GS), 242 pgs., Continued. (PUCO-Columbus, OH) (Volume I) (Part 1 of 2)
08/28/2002 Deposition of James E. Warner filed.
08/28/2002 Deposition of Thomas Carter filed.
08/21/2002 Direct testimony of William B. Smith, Ph.D., filed on behalf of respondent, Columbus Southern Power Co.
08/21/2002 Supplemental direct testimony of J. Derald Morgan, Ph.D., filed on behalf of respondent, Columbus Southern Power Co.
08/21/2002 Supplemental direct testimony of Caroline Irion filed on behalf of respondent, Columbus Southern Power.
08/19/2002 Rebuttal testimony of Richard L. Buchanan, P.E., filed on behalf of complainants by B. Royer.
08/07/2002 Entry ordering that the hearing is scheduled to commence on August 26, 2002, 10:00 a.m., at the Commission's offices, 180 E. Broad Street, 11th floor, Hearing Room 11-C, Columbus, Ohio. (AE)
08/07/2002 Service Notice
07/29/2002 Transcript filed for hearing held July 17, 2002, (GS), 4 pgs., Continued. (PUCO-Columbus, OH)
07/16/2002 Respondent's reply brief in support of motion to strike testimony and exhibits filed by R. Evans.
07/15/2002 Reply memorandum in support of Columbus Southern Power Company's motion to continue hearing filed by R. Evans.
07/15/2002 Stipulation complainant Brian Tomlin vs. Columbus Southern Power Company and American Electric Power Company, Inc. filed by B. Royer.
07/15/2002 Complainants' memorandum contra Columbus Southern Power Company's motion to strike testimony and exhibits filed by D. Moore and B. Royer.
07/12/2002 Columbus Southern Power Company's motion to strike the direct testimony and the exhibits to the direct testimony of John Huwel and to strike any references to the testimony or exhibits in the testimony of complainants' other witnesses filed by R. Evans.
07/12/2002 Complainants' memorandum contra Columbus Southern Power Company's motion to continue hearing filed by B. Royer.
07/11/2002 Entry denying CSP's request for certification; scheduling a hearing at 10:00 a.m. on July 17, 2002, Hearing Room 11-F, Commission offices. (AE)
07/11/2002 Motion to continue hearing and request for expedited ruling and memorandum in support filed on behalf of respondent, Columbus Southern Power Co., by R. Evans.
07/10/2002 Substitution of counsel filed on behalf of respondent, Columbus Southern Power Co., by R. Evans.
07/10/2002 Direct testimony of Caroline Irion filed on behalf of respondent, Columbus Southern Power Co.
07/10/2002 Direct testimony of A. C. Channaiah filed on behalf of respondent, Columbus Southern Power Co.
07/10/2002 Direct testimony of J. Derald Morgan, Ph.D., filed on behalf of respondent, Columbus Southern Power Co.
07/10/2002 Direct testimony of Daniel Downs filed on behalf of respondent, Columbus Southern Power Co.
07/10/2002 Direct testimony of John H. Tucker filed on behalf of respondent, Columbus Southern Power.
07/10/2002 Direct testimony of Richard L. Buchanan, P.E., filed on behalf of complainant by B. Royer.
07/10/2002 Direct testimony of John Huwel filed on behalf of complainants by B. Royer.
07/10/2002 Direct testimony of Dr. Thomas Huston, Ph.D., P.E., filed on behalf of complainants by B. Royer.
07/10/2002 Exhibits to direct testimony of John Huwel filed on behalf of complainants.
07/10/2002 Exhibits to direct testimony of Dr. Thomas Huston, Ph.D., P.E., filed on behalf of complainants.
05/29/2002 Memorandum contra Columbus Southern Power Company's request for certification and approval of interlocutory appeal, filed on behalf of complainants by D. Moore, Jr. and B. Royer.
05/20/2002 Request for clarification and approval of its interlocutory appeal filed on behalf of respondent, Columbus Southern Power Co., by M. Resnik.
05/14/2002 Entry ordering that complaints in Case No. 02-46-EL-CSS and 02-66-EL-CSS are consolidated for the purpose of all future proceedings in these matters; that AEP is dismissed as a party-respondent to the proceedings; that CSP's motion to dismiss is denied; scheduling a settlement conference at 10:00 a.m. on May 28, 2002, Hearing Room 11-F, Commission offices. (AE)
05/14/2002 Service Notice.
05/06/2002 Reply to complainants' supplemental memorandum contra its motion to dismiss, filed on behalf of respondent, Columbus Southern Power Co., by M. Resnik.
04/26/2002 Complainants' reply to memorandum in supplemental support of motion to dismiss.
04/08/2002 Columbus Southern Power Company's Memorandum in supplemental support of its motion to dismiss, filed by M. Resnik.
03/27/2002 Motion for extension of time and request for expedited ruling filed on behalf of respondents, Columbus Southern Power Co. and Ohio Power Co., by M. Resnik.
03/22/2002 Memorandum contra motions to dismiss filed on behalf of complainants by J. Levison and B. Royer.
03/18/2002 Notice of addition of counsel filed on behalf of complainants by J. Levison and B. Royer.
03/18/2002 Motion to consolidate and memorandum in support filed on behalf of complainants by J. Levison and B. Royer.
03/04/2002 Answer and motion to dismiss filed on behalf of respondents, Columbus Southern Power and American Electric Power, by M. Resnik.
01/23/2002 Motion for extension of time to file answer with request for expedited ruling and memorandum in support, filed on behalf of respondent, Columbus Southern Power Co., by M. Resnik.
01/07/2002 Complaint letter and copy of complaint mailed to: Marvin I. Resnik, American Electric Power; and Columbus Southern Power Co.
01/07/2002 In the matter of the complaint of Brian Tomlin (vs) Columbus Southern Power Company and American Electric Power Company relative to the alleged unjust and unlawful failure to comply with the National Electric Safety Code.