DIS - Case Record for 02-0033-EL-BNR Skip to main content
      
      
CASE NUMBER: 02-0033-EL-BNR
CASE DESCRIPTION: AMERICAN ELECTRIC POWER/COLUMBUS SOUTHERN POWER COMPANY
DOCUMENT SIGNED ON: 5/7/2024
DATE OF SERVICE: ________________________________________
10/05/2005 Letter informing that the project on the Beatty-Canal 138 kV Line/McComb 138 kV Line Extension Relocation for Grove City was completed on June 27, 2002 filed by S. Williams on behalf of Columbus Southern Power Company dba American Electric Power.
09/09/2005 Letter stating that this project has been completed filed by S. Williams on behalf of American Electric Power Service Corporation.
03/21/2002 Investigation report construction notice project name McComb 138 kv extension and Beatty - canal 138 kv Line Relocation for Grove City.
01/03/2002 In the matter of the construction notice of American Electric Power, Columbus Southern Power Company, for the relocation of the Beatty-Canal 138 kV Line & McComb 138 kV Ext.