11/23/2004
|
Service Notice |
11/22/2004
|
Entry ordering that the certificate granted by the Board on 10/29/01 to DPL Energy LLC, for construction operation, and maintenance is cancelled and this case closed of record. |
06/17/2004
|
Letter to Com. Schriber stating that in view of changing financial, market and other circumstances has determined that the Allen County plant is no longer an optimal investment and has decided not to proceed with the construction process, filed on behalf of applicant by E. Rizer. |
10/30/2001
|
Service Notice. |
10/29/2001
|
Opinion, Order and Certificate approving the stipulation in its entirety; that a certificate of environmental compatibility and public need for this project be issued; that the certificate shall contain the conditions set forth in Section III of this decision. |
09/05/2001
|
Transcript filed for hearing held August 28, 2001, (BL), 28 pgs. (PUCO-Columbus, OH) |
09/04/2001
|
Transcript filed for hearing held August 30, 2001, (BL), 8 pgs., Submitted. (PUCO-Columbus, OH) |
08/30/2001
|
Joint stipulation and recommendation filed on behalf of applicant by E. Rizer; and the PUCO OPSB staff by T. Lindgren. |
08/14/2001
|
Service Notice. |
08/13/2001
|
Letter regarding a corporate name change, filed on behalf of applicant by M. Goubeaux. |
08/13/2001
|
Staff Report filed. |
08/07/2001
|
Proof of publication filed on behalf of applicant by E. Rizer. (Allen County) |
07/03/2001
|
Service Notice. |
07/03/2001
|
Entry scheduling a local public hearing at 7:00 p.m. on August 28, 2001, at the Harrod Fire Department, Harrod, Ohio; scheduling an adjudicatory hearing at 10:00 am. on August 30, 2001, Hearing Room 11-F, Commission offices. (AE) |
06/27/2001
|
Proof of service letters filed on behalf of applicant by E. Riekert. |
06/27/2001
|
Revenue receipt for application fee filed. |
05/14/2001
|
Correspondence letter to Mr. Frank Frayton, DPL Energy, regarding the application, filed on behalf of the PUCO staff. |
04/17/2001
|
Correspondence regarding a cultural resource survey report, filed on behalf of applicant by E. Riekert. |
04/02/2001
|
Alternate site information for the proposed Harrod Electric Generating Station filed by E. Riekert. |
03/13/2001
|
Service Notice. |
03/09/2001
|
Entry ordering that applicant's motion for waivers of the noted filing requirements is approved and denied as discussed in this entry; that in light of this waiver ruling, applicant supplement its application if necessary. (AE) |
01/24/2001
|
Application for a certificate filed by E. Rickert. |
01/03/2001
|
Motion for waivers of requirements and request for expedited ruling on application filed on behalf of applicant by E. Rizer. (FILED 11/16/00 AND ENTERED INCORRECTLY AS A NEW CASE NO. 00-2251-EL-BGN WHICH HAS SINCE BEEN VOIDED. |
01/02/2001
|
Construction drawings filed on behalf of applicant. |
11/29/2000
|
Application filed on behalf of applicant by K. Guy. |
11/16/2000
|
Motion for waivers of requirements and request for expedited ruling on application filed on behalf of applicant by E. Rizer. |
11/14/2000
|
In the matter of the application of DPL Energy regarding the Lima Electric Generating Station. |