Date FiledSummaryPages
01/16/2003Opinion and Order, ordering complainants request for refund is hereby denied.10
05/13/2002Memorandum contra to complainant's motion to strike, filed on behalf of respondent, Toledo Edison, by K. Kolich. (Original copy)4
05/13/2002Memorandum contra to complainant's motion to strike, filed on behalf of respondent, Toledo Edison Co., by K. Kolich. (Fax copy)3
05/13/2002Motion to strike filed on behalf of complainant by D. Bryan.3
05/08/2002Reply to respondent's initial brief, filed on behalf of complainant by D. Bryan.10
05/07/2002Reply brief filed on behalf of respondent, Toledo Edison Co., by K. Kolich.7
04/22/2002Respondent's certificate of service, that was erroneously omitted from respondent's initial brief, filed by K. Kolich.2
04/22/2002Closing brief on behalf of Plastex Industries, Inc. filed by D. Bryan.13
04/19/2002Brief of respondent Toledo Edison Company filed by K. Kolich.31
04/01/2002 Transcript continue part 2 of 2.185
04/01/2002Transcript of hearing held 3/13/02. (part 1 of 2)200
02/15/2002Service Notice2
02/14/2002Entry setting hearing for 3/13/02, 10:00 a.m., Hearing Room 11-B, at the Commission offices (AE)2
01/04/2002Service Notice.2
01/03/2002Entry ordering that the motion to dismiss counts one and three of the complaint is granted; that discovery be completed by February 8, 2002; scheduling a conference call at 9:00 a.m. on February 8, 2002, to discuss hearing dates.3
11/01/2001Reply memorandum to complainant's memorandum contra, filed on behalf of respondent, Toledo Edison, by K. Kolich.6
10/31/2001Reply memorandum to complainant's memorandum contra, filed on behalf of respondent, Toledo Edison, by K. Kolich. (Fax copy)6
10/09/2001Motion to dismiss and memorandum in support filed on behalf of respondent, Toledo Edison Co., by K. Kolich. (FILED 10/5/01)19
10/05/2001Motion to dismiss and memorandum in support filed on behalf of respondent, Toledo Edison Co., by K. Kolich. (Fax copy)19
08/15/2001Notice of appearance of trial counsel filed on behalf of respondent, Toledo Edison Co., by K. Kolich.2
07/25/2001Service Notice1
07/20/2001Entry scheduling a prehearing settlement conference at 10:00 a.m. on August 29, 2001, Hearing Room 1252, Commission offices; that, if the parties do not reach a settlement at this conference, they shall meet with the attorney examiner at the conclusion of the conference to discuss procedural matters related to the case. (AE)2
12/07/2000Entry scheduling a pre-hearing settlement conference at 10:00 a.m. on December 18, 2000, at the Commission offices; that, if the parties do not reach a settlement at the conference, they shall meet with the attorney examiner at the conclusion of the conference to discuss procedural matters related to the case. (AE)2
11/21/2000Answer filed on behalf of respondent, Toledo Edison, by A. Korkosz.6
11/01/2000Complaint letter and copy of complaint mailed to: Toledo Edison Company, office of the president.1
11/01/2000In the matter of the complaint of Plastex Industries, Inc. (vs) Toledo Edison Company relative to the alleged unjust and unlawful failure to properly bill complainant. (57 pgs.)57