04/25/2001
|
Entry dismissing the complaint and closing this case of record. |
03/08/2001
|
Entry ordering that the complainant contact the examiner within 20 days of the date of this entry if it seeks a hearing in this matters. (AE) |
11/01/2000
|
Request to withdraw without prejudice from this case, filed on behalf of complainant by J. Korff. (1 pg.) |
05/24/2000
|
Entry ordering that a settlement conference be held as set forth on 6/6/2000 at 1:30 p.m. at the offices of the Commission, 180 East Broad St. Columbus, Ohio 432215-3793. (AE) (2 pgs) |
03/21/2000
|
Entry scheduling a settlement conferrence at 10:00 a.m. on April 11, 2000, at the Commission offices. (AE) (2 pgs.) |
03/08/2000
|
Answer and Motion to Dismiss of Ohio Edison Co. Respectfully submitted by, J. Burk (7 pgs) |
02/17/2000
|
In the matter of the complaint of Firestone Energy, Inc. (vs) FirstEnergy Corp. relative to the alleged unjust and unlawful provision of electrical contracting services to an end customer. (7 pgs.) |
02/17/2000
|
Complaint letter and copy of complaint mailed to: H. Peter Burg, FirstEnergy Corp. (1 pg.) |
02/17/2000
|
Complaint letter and copy of complaint mailed to: Anthony J. Alexander, FirstEnergy Corp. (1 pg.) |