Date Filed | Summary | Pages |
01/19/2001 | Memo closing this case of record. | 2 |
10/20/1995 | Letter stating completion date filed on behalf of applicant by T. C. Burgess. (1 pg.) | 1 |
10/06/1995 | Letter stating the construction for the project is scheduled to commence on October 9, 1995 filed on behalf of applicant by T. C. Burgess. (1 pg.) | 1 |
09/14/1995 | ICN #0003 Letter in response to Letter of Notification, filed by K. Wissman, OPSB staff. | 1 |
09/13/1995 | ICN #0002 Investigation report approving the Letter of Notification, filed by J. O'Dell, OPSB staff. | 1 |
08/29/1995 | In the matter of the letter of notification of Ohio Edison Chamberlin-Valley (CF) 138 kV & Chamberlin-West Akron 138 kV replace steel pole. | 29 |