Case Record For:

86-2275-EL-BTX

File a Public Comment
Case Title: OHIO EDISON COMPANY
Status: AR-Archived
Industry Code: EL-ELECTRIC
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 12/9/1986
Date Closed: 12/14/1987
Printable Docket Card Service List
View All
1 - 15 of 31 documents 1 /  3 
Date FiledSummaryPages
10/16/2000ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates.13
10/16/2000 ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates 7
10/16/2000ICN #0029 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. (6 pgs.)6
08/07/1992ICN #0028 Information response filed on behalf of applicant by T. Burgess.0
05/28/1992ICN #0027 Semi-annual report of citizen complaints and equipment problems, stating that the previous six months of operation (November 1, 1991 - April 30, 1992) had no citizen complaints or equipment problems associated with this project, filed on behalf of applicant by T. Burgess.0
01/03/1992ICN #0026 Second semi-annual report of citizen complaints and equipment problems that may occur during the two-year period of initial operation, filed on behalf of applicant by T. Burgess.0
08/06/1991ICN #0025 First semi-annual report of citizen complaints and equipment problems, filed on behalf of applicant by T. Burgess.0
12/13/1990ICN #0024 Letter filed on behalf of the applicant stating that the transmission line tap was completed on November 20, 1990 filed by T. Burgess.0
11/16/1989ICN# 0023 Letter filed by J. Kennedy on behalf of the OPSB stating that the transmission lines are consistent to the application, and construction may proceed.0
11/09/1989ICN# 0022 Engineering drawings filed on behalf of the applicant by T. Burgess.0
12/14/1987ICN. #0021 Opinion, Order, and Certificate issued, Ordering that the Administrative Law Judge's Report and Recommenda- tions be adopted within the Board's order and certificate in this case as though fully restated therein; Ordered that Ohio Edison Company comply with all applicable laws and regulations in this matter and with all conditions contained within the joint stipulation adopted herein. (AE)0
12/14/1987ICN. #0020 Comments to report and recommendations of administrative law judge filed by T. Kayuha on behalf of applicant.0
12/10/1987ICN. #0019 Comments of Staff of Ohio Power Siting Board on report and recommendations of administration law judge filed by J. Payne, Jr.0
11/24/1987ICN# 0018 Report and recommindations of ALD filed by E. Cruttenden.0
11/03/1987ICBN. #0016 Joint Stipulation of Findings and Recommenda- tions filed by T. Kayuha on behalf of applicant and M. Malone on behalf of the PUCO staff.0
 
1 /  3 
      
      
Attorney General:
Attorney Examiner: