Date Filed | Summary | Pages |
10/16/2000 | ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. | 13 |
10/16/2000 |
ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates
| 7 |
10/16/2000 | ICN #0029 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. (6 pgs.) | 6 |
08/07/1992 | ICN #0028 Information response filed on behalf of applicant by T. Burgess. | 0 |
05/28/1992 | ICN #0027 Semi-annual report of citizen complaints and equipment problems, stating that the previous six months of operation (November 1, 1991 - April 30, 1992) had no citizen complaints or equipment problems associated with this project, filed on behalf of applicant by T. Burgess. | 0 |
01/03/1992 | ICN #0026 Second semi-annual report of citizen complaints and equipment problems that may occur during the two-year period of initial operation, filed on behalf of applicant by T. Burgess. | 0 |
08/06/1991 | ICN #0025 First semi-annual report of citizen complaints and equipment problems, filed on behalf of applicant by T. Burgess. | 0 |
12/13/1990 | ICN #0024 Letter filed on behalf of the applicant stating that the transmission line tap was completed on November 20, 1990 filed by T. Burgess. | 0 |
11/16/1989 | ICN# 0023 Letter filed by J. Kennedy on behalf of the OPSB stating that the transmission lines are consistent to the application, and construction may proceed. | 0 |
11/09/1989 | ICN# 0022 Engineering drawings filed on behalf of the applicant by T. Burgess. | 0 |
12/14/1987 | ICN. #0021 Opinion, Order, and Certificate issued, Ordering that the Administrative Law Judge's Report and Recommenda- tions be adopted within the Board's order and certificate in this case as though fully restated therein; Ordered that Ohio Edison Company comply with all applicable laws and regulations in this matter and with all conditions contained within the joint stipulation adopted herein. (AE) | 0 |
12/14/1987 | ICN. #0020 Comments to report and recommendations of administrative law judge filed by T. Kayuha on behalf of applicant. | 0 |
12/10/1987 | ICN. #0019 Comments of Staff of Ohio Power Siting Board on report and recommendations of administration law judge filed by J. Payne, Jr. | 0 |
11/24/1987 | ICN# 0018 Report and recommindations of ALD filed by E. Cruttenden. | 0 |
11/03/1987 | ICBN. #0016 Joint Stipulation of Findings and Recommenda- tions filed by T. Kayuha on behalf of applicant and M. Malone on behalf of the PUCO staff. | 0 |