Date Filed | Summary | Pages |
12/23/2020 | Notice of the Completion of Construction of Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |
03/31/2020 | Notice of Commencement of Construction on Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |
02/25/2020 | Service Notice | 2 |
02/25/2020 | Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB. | 5 |
12/03/2019 | Application of American Transmission Systems, Inc. for the Construction Notice of Mayfield-Eastlake Q-3 & Q-4 138 kV Transmission Line Tap to Nathan Substation Project filed by M. Hunsche. | 56 |
11/18/2019 | In the matter of the Pre-Application Notification Letter Revised Mayfield-Eastlake Q-3 & Q-4 138kV Transmission Line Tap to Nathan Substation Project. | 2 |