Date Filed | Summary | Pages |
08/21/2019 | Case Action Form to Close Case electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. | 2 |
10/26/2017 | Letter of Notification that the construction on this Project was completed on October 23, 2017 filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
11/21/2016 | Letter of Notification stating that construction on this project commenced on November 17, 2016 filed on behalf of FirstEnergy Service Company by N. Bryksenkova. | 1 |
11/07/2016 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
08/19/2016 | Proof of Publication electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.(Trumbull County) | 3 |
08/17/2016 | Letter of notification for 345kV transmission line loops to and raining 138kV transmission lines for clean energy future Lordstown, LLC project filed by American Transmission Systems Incorporated. | 41 |
08/08/2016 | In the matter of the Pre-Application Notice of Application Future Lordstown LLC Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 2 |