DIS - Case Record for 15-1756-EL-BLN Skip to main content

Case Record For:

15-1756-EL-BLN

File a Public Comment
Case Title: Nottingham-Freebyrd 138kV Transmission Line Adjustment
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BLN-letter of notification
Date Opened: 11/5/2015
Date Closed: 8/9/2019
Printable Docket Card Service List
View All
1 - 10 of 10 documents 1 /  1 
Date FiledSummaryPages
08/09/2019Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.2
11/13/2017Notification electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.2
02/15/2017Notice of Start of Construction and In-Service Date for the Nottingham-Freebyrd 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company.2
02/16/2016Letter of Notification re Construction Start Date electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.2
02/02/2016Correspondence Accepting Staff's Conditions electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.2
01/28/2016Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB.6
01/21/2016Correspondence electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.3
11/20/2015Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.4
11/05/2015Letter of Notification Part 2 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.78
11/05/2015In the matter of the Letter of Notification Part 1 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.12
 
1 /  1 
      
      
Attorney General:
Attorney Examiner: