DIS - Case Record for 15-0288-EL-BNR Skip to main content

Case Record For:

15-0288-EL-BNR

File a Public Comment
Case Title: Avon-Beaver No1 and No2 345kV Transmission Line Extensions to Lake Avenue Substation
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 3/31/2015
Date Closed:
Printable Docket Card Service List
View All
1 - 5 of 5 documents 1 /  1 
Date FiledSummaryPages
12/05/2016Construction Notice that project was completed on November 30, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.1
03/21/2016Notice that construction on the Avon-Beaver No.1 and No.2 345 kV Transmission Line Extensions to Lake Avenue Substation Project was approved by the Board on May 13, 2015, commenced on March 11, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.1
05/06/2015Staff Report of Investigation electronically filed by Mrs. Yvonne W. Cooper on behalf of Staff of OPSB.3
04/01/2015Construction notice of American Transmission System Incorporated for Avon-Beaver No. l and No. 2 345 kV Transmission Line Extensions to Lake Avenue Substation Project filed by N. Bryksenkova.12
03/31/2015In the matter of the Notification of Construction (Construction Notice) for the Avon-Beaver No 1 and No 2 345 kv Transmission Line Extensions to Lake Avenue Substation electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.13
 
1 /  1 
      
      
Attorney General:
Attorney Examiner: