Date FiledSummaryPages
01/08/2015Letter of notification that this project was completed on December 20, 2014, filed by W. Beutler on behalf of FirstEnergy Service Company.1
09/26/2013Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB3
08/23/2013Service List for the Tangy Substation Expansion Project filed by J. Thacker on behalf of FirstEnergy Service Company.11
08/23/2013In the matter of the construction notice for the Tangy Substation Expansion Project.7
 