DIS - Case Record for 10-2787-RR-RCP Skip to main content

Case Record For:

10-2787-RR-RCP

File a Public Comment
Case Title: COLUMBUS AND OHIO RIVER RAILROAD/NEWARK LICKING COUNTY
Status: CL-CLOSED
Industry Code: RR-RAILROAD
Purpose Code: RCP-Railroad Crossing Protection
Date Opened: 11/22/2010
Date Closed: 11/30/2012
Printable Docket Card Service List
View All
1 - 15 of 31 documents 1 /  3 
Date FiledSummaryPages
11/30/2012Case action form closing cases with an effective date of 11/30/2012.1
11/30/2012Memo stating that the grade crossing improvements/upgrades in the above referenced cases have been completed and installed.1
11/01/2012Service Notice2
11/01/2012Request for a 30 day extension to complete the project filed by D. Birrell on behalf of Columbus and Ohio River Railroad.1
10/31/2012Attorney Examiner Entry granting CUOH's request for a 30-day extension of time of the completion date, ordering CUOH to complete the project by 12/01/12. - electronically filed by Sandra Coffey on behalf of Scott Farkas, Attorney Examiner, Public Utilities Commission of Ohio.3
10/31/2012Request for 30 day extension of time to complete project filed by D. Birrell on behalf of Ohio Central Railroad Company, Inc.1
10/31/2012Memo regarding that staff finds the request well made, and recommends that the Attorney Examiner grant the request filed by G. Martin, Staff.1
09/28/2012Service Notice2
09/28/2012Attorney Examiner Entry granting CUOH's request for a 30-day extension to 11/01/12 to complete the project. - electronically filed by Sandra Coffey on behalf of Scott Farkas, Attorney Examiner, Public Utilities Commission of Ohio.3
09/27/2012Letter informing the Commission that the Columbus &. Ohio River Railroad (CUOH) install new light and gate assemblies at the N Cedar St/SR 79 grade crossing in conjunction with ODOT roadway work and traffic signal installation and preemption at the SR 79/SR16 on and off ramp. The ordered completion date for the project was September 8, 2011. By subsequent Entries, the deadline for this project was extended to October 1, 2012. filed by Staff. 1
09/27/2012Request for extension filed by D. Birrell on behalf of Ohio Central Railroad Company, Inc.1
09/27/2012Letter requesting a 30 day extension filed by D. Birrell on behalf of Columbus and Ohio River Railroad Incorporated. 1
05/30/2012Service Notice2
05/30/2012Entry ordered, that CUOH's extension request be granted and that CUOH complete the project by October 1, 2012.2
05/14/2012Staff Review and Recommendation that the Attorney Examiner grant this extension, filed by the Staff of the PUCO.2
 
1 /  3 
      
      
Attorney General:
Attorney Examiner:
Farkas, Scott